First female welder in the North Sea
She worked for E & C.
Norpipe 36/22 A booster platform unmannedSeabed subsidence
She worked for E & C.
Norpipe 36/22 A booster platform unmannedSeabed subsidence
Different systems for rotating personnel between work and leisure functioned in parallel on the drilling rigs during the early years of oil exploration in the Norwegian North Sea. The most common practice was nevertheless one week on and one off. To get a holiday, people carried on working offshore until they were entitled to three weeks free in one go.
However, this arrangement proved impractical – particularly for workers who going offshore or returning home on a Saturday or Sunday. They never got a full weekend off. To stagger such change-overs, the schedule was extended to eight days offshore with eight days free. One work period in five was also dropped, so every fifth free spell was 24 days long.[REMOVE]Fotnote: This gave a working time which averaged 38 hours per week and 1 824 hours per year after holidays. That corresponded to shift work on land.
When Norway’s Working Environment Act (WEA) came into force in 1977, the permitted length of a continuous shift on land was cut. But there was no assurance that this would be applied offshore. In its original form, the Act did not permit the 12-hour working day normal on all offshore installations. So amendments were needed to adapt the legal provisions to fixed platforms.[REMOVE]Fotnote: The Act specified that working time was 36 hours over seven days for work carried out around the clock throughout the week. That represented 1 877 hours a year on average. Adjusting this for four weeks of holiday gave a net working time of 1 733 hours.
The Norwegian Petroleum Directorate argued that reducing working time offshore was impractical, with the “special character” of the oil industry requiring exemptions.[REMOVE]Fotnote: Ryggvik, H, 1999, “Fra forbilde til sikkerhetssystem i forvitring: Fremveksten av et norsk sikkerhetsregime i lys av utviklingen på britisk sokkel”, Working Paper, Volume 114, Centre for Technology and Culture, University of Oslo, printed edition. Oslo: Centre for Technology, Innovation and Culture (TIK), University of Oslo: 16. As early as 1975, however, Ekofisk operator Phillips Petroleum had agreed to working hours for its own personnel which accorded with the provisions proposed for the new Act. A royal decree of 9 July 1976 extended the existing Worker Protection Act, with certain exceptions, to the fixed installations offshore on a temporary basis.
The WEA was then applied to these facility in 1977.[REMOVE]Fotnote: Ryggvik, H, 1999, “Fra forbilde til sikkerhetssystem i forvitring: Fremveksten av et norsk sikkerhetsregime i lys av utviklingen på britisk sokkel”, Working Paper, Volume 114, Centre for Technology and Culture, University of Oslo, printed edition. Oslo: Centre for Technology, Innovation and Culture (TIK), University of Oslo: 18. This meant that offshore workers had their working time regulated and acquired legal safeguards against unfair dismissal. After long discussions, the North Sea schedule was by and large established as two weeks working offshore and three weeks free on land.
But the WEA was not applied to floating units such as rigs, and working time in that part of the oil industry continued to be regulated by Norway’s Ship Labour Act.
Norway’s legislation on paid holidays was amended in 1981 to give everyone a legal right to four weeks and one day off. The latter was nicknamed the “Gro Day” after Gro Harlem Brundtland, the Labour premier of the day. This meant the two weeks on/three weeks off schedule now imposed too many working hours. It was decided that the extra would be compensated as 25 hours of overtime per year.[REMOVE]Fotnote: Working time was reduced from 1 752 to 1 727 hours.
Agreement was reached in the 1986 collective pay negotiations on a 7.5-hour normal working day and a 37.5-hour week. Personnel both on land and offshore working a continuous shift also had their weekly hours cut 33.6.[REMOVE]Fotnote: Net working hours after deducting holidays were reduced from 1 752 to 1 727. To comply with these new terms, the offshore schedule was altered to two weeks at work, three weeks ashore, two weeks at work and four weeks on land.
When the Gro Day was introduced in 1981, the Labour government originally proposed introducing a full week’s extra holiday in stages over three years. But that failed to materialise. In 2000, the Norwegian Confederation of Trade Unions (LO) proposed a fifth holiday week for all employees, which would thereby reduce the number of hours in a work-year.[REMOVE]Fotnote: That involved an additional four free days of 7.5 hours offshore (32 hours). The hours to be worked were then reduced from 1 612 to 1 580. That demand was accepted, and most workers could thereby enjoy five weeks off. This naturally had consequences offshore, but implementing it there was not a straightforward matter.
A schedule of two weeks at work and three/four weeks at home had been 19 hours short of a normal work-year. That was overcome by deducting this time from pay or leaving the first 11 hours of overtime unpaid.[REMOVE]Fotnote: Sande, Leif, “Arbeidstiden på sokkelen”, Sysla – meninger, 11 March 2015.
The new holiday deal meant that an offshore worker would be doing 12 extra hours per year. This was initially paid as overtime, which the unions found unsatisfactory. They demanded the full holiday entitlement awarded to everyone else through the introduction of a schedule of two weeks on and four off. In 2002, the Norwegian Oil Industry Association (OLF – today the Norwegian Oil and Gas Association) allowed local deals under the offshore agreements to adopt this two-four scheme. All the companies subject to these agreements introduced the new schedule. ConocoPhillips was among the operators to do this, in its case covering the Greater Ekofisk Area.
However, the two-four system meant workers were falling short of a work-year by 122 hours.[REMOVE]Fotnote: Working 12 hours a day for 14 days, followed by four weeks off, means that an employee works 168 hours every six-week period. That adds up to 1 460 hours per year. Annual pay was thereby cut by 7.71 per cent to take account of the reduced time worked.[REMOVE]Fotnote: Norwegian Official Reports (NOU) 2016:1, Arbeidstidsutvalget — Regulering av arbeidstid – vern og fleksibilitet. https://www.regjeringen.no/no/dokumenter/nou-2016-1/id2467468/sec16. Other conditions were also set on Ekofisk. The whole offshore organisation was to be reviewed to find efficiency gains, and the agreement specified that the change would not lead to an increase in the workforce.[REMOVE]Fotnote: Pioner, “2-4-ordningen innføres”, March 2003.
Åm was born at Årdal in the Sogn district of western Norway in 1944, and grew up in Oppdal and Volda/Ørsta where he proved an able pupil at school.
He opted to study mining engineering at the Norwegian Institute of Technology (NTH) in Trondheim, graduating with honours in 1967.
Åm’s first job was with the Norwegian Geological Survey (NGU), again in Trondheim, where he worked and conducted research for six years. One of his jobs was to interpret aeromagnetic measurements of sub-surface rocks made from the air, which provide valuable information on geology and prospects for finding petroleum. In a series of publications, he described the big sedimentary basins identified in the Skagerrak between Norway and Denmark and in the Norwegian and Barents Seas.
He joined the Norwegian Petroleum Directorate (NPD) in 1974, serving as a section head in the resource department and a principal engineer in the safety department.
That was followed by three years with Statoil, where he became the state oil company’s first vice president for research and development. His appointments at the time included chairing a research programme on offshore safety, which led to legislation enacted by the Storting (parliament) and a bigger research effort.
Åm secured a job with Phillips in 1982 and was soon sent to the head office at Bartlesville in Oklahoma to get better acquainted with the company and its corporate culture.
After a year in the USA, he returned to the company’s Tananger office outside Stavanger and became the first Norwegian to serve as offshore manager for the Greater Ekofisk Area (GEA).
That put him in charge of 23 platforms, with responsibility for the waterflooding programme as well as the project to jack up a number of the installations. These major developments extended the producing life of the GEA and sharply increased estimates for recoverable reserves from its fields.
Åm led this work during difficult times, with low oil prices and the need to implement cost savings and overcome substantial financial challenges. As if that were not enough, he also taught at the University of Bergen from 1985 to 1990 as an adjunct (part-time) professor of applied geophysics.
After heading operations in the Permian and San Juan Basins at Odessa, Texas, from 1988-91, Åm became the first Norwegian president and managing director for Phillips Petroleum Norway.
That put him in charge of 3 000 employees in the GEA as well as in Tananger, Oslo, Teesside and Emden. This was when a redevelopment of Ekofisk was planned, along with the future cessation and removal of old platforms.[REMOVE]Fotnote: https://www.fylkesmannen.no/globalassets/fm-rogaland/dokument-fmro/felles-og-leiing/brev-og-artiklar/fm-tale-til-knut-am.pdf
By 1996, Åm was back in Bartlesville – now as vice president and head of all exploration and production in Phillips. He stayed in that job until retiring in the USA during 1999.
But his working life did not end there. Appointments from 1999 to 2007 include membership of the Statoil board – and many similar posts can be mentioned.
Åm has been president of the Norwegian Geological Council and the Norwegian Petroleum Society, and chair of the Norwegian Oil Industry Association (now the Norwegian Oil and Gas Association).
He led the exhibition committee of the 1996 ONS oil show in Stavanger, and has chaired Bergen’s Christian Michelsen Research institute as well as the industrial council of the Norwegian Academy of Science and Letters.
In addition to chairing Hitec ASA, he has been a director of several technology companies.
Mention must also be made of the improved recovery committee appointed by the Ministry of Petroleum and Energy with Åm as chair. This produced a report in September 2010 which presented 44 specific measures for improving the recovery factor on the Norwegian continental shelf (NCS).
Through his work and many appointments, Åm has been acclaimed for a combination of expertise, creativity and determination. He also demonstrated the ability to tackle the requirements of Norway as a nation as well as the industry and its employees – not least with regard to the working environment and safety in a demanding and risky offshore industry.
In retirement, Åm is an optimist – with regard to the climate as well. “I’m very concerned with nature, but believe we should extract the resources it’s given us,” he told Otium in 2016.
“Norway could have a long and good future in the oil and gas industry if people give it more support. Exploring for new deposits is important, but we should also seek to achieve a far better recovery factor from both new and existing fields.”
“You can naturally concentrate on life’s negative aspects. Then everything’s simply awful. I think you’ll be a far happier person if you prefer to see the positive side of life. I call that self-motivation. We need more of that in the energy sector.”[REMOVE]Fotnote: https://api.optimum.no/sites/default/files/PDF/optimum-magasinet-2016.pdf
Early promotion and trust followed, and he served as an offshore installation manager (OIM) for more than 33 years in the Greater Ekofisk Area.
Kristensen recalls that he was a committed young man in the early 1970s – an open, curious and plain-speaking person who was not afraid to criticise health, safety and environmental (HSE) conditions.
The working style he encountered offshore suited him well, ready as he was to speak his mind. “I’ve undoubtedly been a loud-mouth. I’m used to having zealous people in the Family With grand-parents and a father who served as mayors, which is perhaps why I don’t quite know when to keep quiet.”
Thinking back to working conditions when he started in petroleum industry, he recalls living on Gulftide, Norway’s first production facility, and says it was fascinating.
“This was an old jack-up rig, with the helideck installed on planks. We were four to a cabin, and things were pretty shabby. Primitive conditions prevailed, to put it mildly.”
The workplace at the time was characterised by the presence of the Americans, and confusions frequently arose between them and those who were not particularly good at English.
“It was very unusual,” reflects Kristensen. “We were trained up by the Americans, of course – they were the ones who knew about this business. There were a lot of misunderstandings among the Norwegians, people who pretended to understand the messages they were given about what jobs to do. Both serious and funny situations occured. Those of us who’d been to sea undoubtedly had an advantage in that we knew the language a bit better. The rest were fishermen and smallholders and ordinary people from the Districts in Western Norway who didn’t speak much English. Offshore terminology wasn’t easy for people who didn’t have the language.”
He quickly grasped the ethos in this working environment. “The Americans often only gave you one chance. If you showed that you could cope with your job, you won trust, new opportunities and more responsibility.”
Given his background in the Norwegian merchant marine, however, Kristensen reacted negatively to a number of the conditions which prevailed at the time. “I was one of the youngest then, and that wasn’t always easy because there were a number of older and more experienced people who felt they had a ‘monopoly of brains’,” he comments. “And quite a lot were pushy. “Working conditions weren’t orderly, with proper employment contracts like I was used to from my time at sea thanks to the Norwegian Seamen’s Union – unionisation and the like.”
He adds that he is grateful for everything he learned from the Americans, but that they at the time were not particularly keen on unions and the Norwegian concept of collaboration between employers and employees. “They thought it was enough to enter into agreements on a man–to–man basis or with the company, and saw no need to organise this via trade unions.”
Given his views, it is not surprising that he became involved at an early stage with the Ekofisk Committee by serving as secretary to Øyvind Krokvik, who was first head of this union.
Kristensen explains that he has been committed throughout his career to involvement and worker participation and to good collaboration between unions, the safety service and management. That was particularly important during the early years of the petroleum industry on the NCS, he emphasises. His experience of union work accompanied him into various senior posts on Ekofisk.
With a gleam in his eye, he says the following about his promotion: “Acquiring managerial responsibility early on may have had something to do with my involvement with the union. “Putting in place systems for worker participation and collaboration was particularly important in the early years of Norway’s offshore industry.
“I played a part in establishing the parameters which govern industrial relations out on the field today, with unions and the safety delegate service.
I became the country’s youngest OIM at the age of 24, and served as a manager out there for 41 years.
They may have thought ‘he’s more trouble than we need, so we’ll just promote him up and then be quit him’.”
Kristensen reports that he has been preoccupied throughout his managerial career with ensuring that “things are genuine” – that a manager must understand and personally be part of “the home team”. He explains that as the ability to understand a position from the standpoint of the various parties involved, and adds that he has thrived offshore with a living and working community. This he defines as one “where you get close to people, where everyone is seen and heard, and where they understand that they play an important role in reaching a common goal”.[REMOVE]Fotnote: Pionèr, ONS 2018: 8.
It did not take him long to learn how to adjust his management style to the offshore environment, but admits that this approach has developed over the years. “The leadership culture which dominated on the platforms during the early years undoubtedly influenced me a bit. I was probably very inflexible and saw things in black-and-white, but have become more judicious and considered over time.
“Nobody left my office earlier in any doubt about what I meant. I thought that saved a lot of time. But I can’t have been too bad, or I wouldn’t have held down the job for so long.”
Kristensen’s long service makes him unique on Ekofisk, and he has thought a lot about management. His expressed strategy has been to get people on side over HSE through commitment and integrity – and without any “second agenda”.
“Working in the Ekofisk Complex with 600-700 people is an unusual experience,” he observes. “I held the same job as the man in charge for 20 years. “That means you’re ‘on stage’ the whole time, and attend 10-12 HSE meetings every week. You’ve got to get people committed, drive a doctrine and sell a message.” This involves getting what people have to concentrate on implanted in their hearts and minds so they can contribute to their own safety and that of others, he explains.
“You must be genuine, and your own integrity must be order. You have to build trust, and not least display respect for your audience.”
“What’s been a powerful help for me is that I’m on the home team. I’ve been a skilled worker myself and have been through most things.”
Kristensen emphasises several times that he regarded the unions, their elected officers and the safety delegates as a resource in this work.
“The tripartite collaboration pursued in the petroleum industry between government, companies and unions functions very well,” he concludes. “This is about informing and involving people, and ensuring that decisions aren’t taken over their heads. Our company has achieved that in a positive way.”
“The fact that Ekofisk is a mature field and ConocoPhillips is a mature company also has something to do with it. Cooperation with the Petroleum Safety Authority Norway and other authorities is also very good.”
Kristensen denies that union-management collaboration has become more strained during the downturns experienced by the petroleum industry. “Strained and strained – we must adjust to external conditions and try to protect the jobs needed to safeguard the industry. But nobody’s ever been made redundant by this company. That’s worthy of respect. “
“Downsizing has been solved with severance packages. People have often been given early retirement. From that perspective, it’s been a privilege to work for an operator company.”
After almost 46 years with the company, Kristensen’s commitment to continuous improvement, good safety and high production regularity is as strong as ever. Recognising that substantial progress has been made in the HSE area over the years he has worked in the industry, he affirms that this issue is closest to his heart.
“We’ve staked out the path as we’ve advanced. We don’t accept incidents and accidents. We take a completely different approach to risk today. Accidents which do occur are used for all they’re worth in an effort to say to ourselves: ‘this has actually happened, but it’s our duty to learn from it’.”
Kristensen has personally experienced accidents and injuries at close hand, and thereby knows the importance of preventive safety work to protect people, the environment and equipment.
He will never forget some incidents – and immediately mentions the Alexander L Kielland disaster in 1980 With 123 casualties. An article in local daily Stavanger Aftenblad as recently as 2012, with photos of all those who have died on duty on the NCS since 1966, made a big impression on him.
Britain’s Piper Alpha explosion in 1988, when 169 people were killed, is another major incident he recalls. His conclusion is that the petroleum sector has not been a Promised Land for all.
The former OIM proudly mentions a number of HSE improvements which have partly been the result of technological advances in the industry during his time. But he warns about hazards which still exist, such as vessels drifting out of control. A well-known incident on New Year’s Eve in 2015 made a particularly strong impression on him.
A 150000 tons, unmanned barge had come loose and was threatening to collide with installations on Ekofisk. Several hundred workers from this field and neighbouring Valhall were flown to safety and production was shut down. The barge passed the platforms at a distance of about one nautical mile, but Kristensen found the actual incident and the threat it posed frightening.
“Drifting vessels which come loose in rough weather, which can get pretty challenging out there, are perhaps the biggest hazard we now face. Luckily we have good procedures to handle such challenges.”
Such incidents and near-misses are regarded by Kristensen as a reminder that the petroleum industry is under an obligation to learn the necessary lessons. He points to the potential for learning from other industries, and emphasises the good collaboration which prevails across the company. Mechanical handling provides a good example, he says.
“Things can go terribly wrong. After fatal accidents in the 2000s, we established a work group which held monthly meetings. I took part as technical manager for these facilities. We involved everyone in the logistics chain on land, at the base and on the platforms. That attracted so much attention and such great improvements that we’ve now managed to prevent virtually all undesirable conditions in this area.”
Despite good systems and routines, colleagues on the installations are Kristensen’s most important reminder of the responsibility he has had as an OIM on Ekofisk.
“Experiences from my early years meant that I have become particularly attentive to HSE – and I was involved in quite a lot, of course. But this mostly relates to the individual who gets injured on your watch and on your shift – in other words, the people you work with. They stood on the drill floor and worked so that the sparks flew around their ears. Having only two-three fingers used to confer ‘status’.”
He notes that improvements have a lot to do with technological progress. Much risk has been eliminated by automating a great deal of the work which used to be done manually.
“But we still have more than enough opportunities to injure ourselves. This has a lot to do with awareness – being present in the real world, making sure you’re focused. That’s actually expected for 12 hours at a time.”
A respectful attitude to his big responsibilities and duties was maintained by Kristensen to his last working day. “Emergency preparedness is like being at war – you do what you’re told. But you feel it. Although we’ve trained so long at this, you’re still conscious of being responsible for several hundred lives. Taking a wrong decision could … You must act on the basis of the information you’ve got, not what you know many months later. When you tackle it, however, you get a sense of mastery at solving the problem together with an outstanding emergency response organisation on land. Ultimately, though, you’re the skipper on your own ship.”
Kristensen has finally retired from ConocoPhillips, giving him time to reflect over his own commitment and lifestyle offshore as it affected him and his family.
“For my own part, I must say that it’s had a price,” he admits. “I couldn’t get involved in politics or organisations, for example. I was only at home half of the time. I followed up the kids when I was at home, of course, but never felt I could be active in associations and so on, contribute the way I’d have liked.”
He has found the transition to retirement unaccustomed in many ways. “Simply remembering that I’m not going offshore is a big change, for example. I had to deal with so many challenges right up to my last day at work that it’s been impossible to prepare anything. I ought to have thought about and planned retirement a bit better, of course, but I’ll undoubtedly find something to do when I want to.”
The aim of this facility – an extension to the Ekofisk South project – was to increase waterflooding on the southern flank of the Ekofisk reservoir in order to maintain oil and gas production.
An amended plan for development and operation (PDO) of Ekofisk South was approved by the Ministry of Petroleum and Energy on 7 September 2017.
This involved installing a new seabed template with four water injection wells, and represented a continuation of the well-established Ekofisk production strategy based on waterflooding.[REMOVE]Fotnote: https://www.regjeringen.no/no/aktuelt/okt-utvinning-pa-ekofiskfeltet/id2570011/.
The template was installed in September 2017, with a technical solution similar to that used on the seabed facilities already installed – Ekofisk 2/4 VA and 2/4 VB.[REMOVE]Fotnote: Pionér, no 2, ConocoPhillips, 2018.
In addition to the structure itself, including wellheads and Xmas trees, the installation comprised control modules with umbilicals connected to the existing waterflooding system.
The 2/4 VC facility receives injection water from Eldfisk 2/7 E, while power and control signals come from Ekofisk 2/4 M. It is run from the Ekofisk 2/4 K control room.
When fully developed, overall injection capacity for this subsea installation will be 80 000 barrels per day through the four wells.
The water pipeline and umbilical to 2/4 VB were extended to 2/4 VC. Well operations on the latter began on 24 May 2018 with a view to starting injection before the end of the year.
Do you want to see the development of the Ekofisk area from 1971 to 2001 click here.
To follow the development of the field further from 2008 to 2017 click here.
This platform rests on a steel jacket built by Dragados at Cadiz in Spain. The module support frame (MSF) and topsides were fabricated by Energomontaz at Gdansk in Poland and completed at Kværner Egersund.
The topsides were installed in July 2013. Petroleum and energy minister Tord Lien performed the official inauguration of 2/4 Z and the Ekofisk South project on 29 October 2013,13 just four days after the platform came on stream.14
No control room is provided on 2/4 Z, but it has a local equipment room (LER) which is not permanently manned. The platform is monitored and remotely controlled from the control room on Ekofisk 2/4 J, but can also be run from the operations centre in Tananger.
2013-10 – Historisk dag for Ekofisk og Norge åpning av Ekofisk 2-4 Z – regjeringen-no
So successful had the 2/4 VA facility proved to be that it was copied for 2/4 VB as an eight-well template, also delivered by FMC at Kongsberg.
Similarly, the wells on 2/4 VB were drilled by Maersk Innovator. The well operation department completed installation of the template, manifolds and casing for the eight subsea wells.
Seabed installations carried out by Subsea 7 comprised a five-kilometre pipeline for water from the Eldfisk Complex as well as a diver-installed T piece welded into the existing pipeline from Eldfisk 2/7 E to Ekofisk 2/4 K.
This assignment also covered laying three kilometres of umbilicals combining hydraulic lines and fibreoptic cables from 2/4 VA, so that 2/4 VB could also be remotely operated from land.
Primarily located in production licence PL 018, along with Ekofisk, the other seven fields are West Ekofisk, Tor, Eldfisk, Albuskjell, Edda, Cod and Embla.
Furthermore, six of the eight – with Embla and Cod as the exception – comprise two geological formations. One is known as the Ekofisk formation, with the Tor formation as the other. See the article on sea scurf.
The graph in figure 2, which presents collective production of oil, gas and condensate over time in million standard cubic metres of oil equivalent (scm oe), shows Ekofisk’s dominant position – both historically and today.
With the exception of four years, overall output from the seven other fields has never achieved the same volume as Ekofisk’s own production.
The effect of waterflooding on Ekofisk, which got going seriously in 1987, can be clearly seen in the production curve. This rose from less than 10 million scm oe per annum to more than 20 million.
On 1 July 2019, operator ConocoPhillips submitted a plan for development and operation (PDO) which covered reopening the Tor field (Tor II).
This will involve the investment of about NOK 6 billion, with a planned production start in late 2020, and is expected to yield an estimated 10 million scm oe.
Furthermore, the licensees have initiated concept studies for further development of the northern flank of Eldfisk (Eldfisk II). Both subsea solutions and a simple unmanned platform are under consideration.[REMOVE]Fotnote: https://petro.no/nyheter/conocophillips-vurderer-a-bygge-ny-plattform-pa-eldfisk-nord
Development of the Tommeliten Alpha formation, which has only ranked as a discovery so far, is also being assessed.[REMOVE]Fotnote: https://petro.no/nyheter/forbereder-mulig-utbygging-tommeliten-alpha